My new kitchen clock

Derek Jones from The Shape of Code

After several decades of keeping up with the time, since November my kitchen clock has only been showing the correct time every 12-hours. Before I got to buy a new one, I was asked what I wanted to Christmas, and there was money to spend :-)

Guess what Santa left for me:

Hermle Ravensburg clock.

The Hermle Ravensburg is a mechanical clock, driven by the pull of gravity on a cylindrical 1kg of Iron (I assume).

Setup requires installing the energy source (i.e., hang the cylinder on one end of a chain), attach clock to a wall where there is enough distance for the cylinder to slowly ‘fall’, set the time, add energy (i.e., pull the chain so the cylinder is at maximum height), and set the pendulum swinging.

The chain is long enough for eight days of running. However, for the clock to be visible from outside my kitchen I had to place it over a shelf, and running time is limited to 2.5 days before energy has to be added.

The swinging pendulum provides the reference beat for the running of the clock. The cycle time of a pendulum swing is proportional to the square root of the distance of the center of mass from the pivot point. There is an adjustment ring for fine-tuning the swing time (just visible below the circular gold disc of the pendulum).

I used my knowledge of physics to wind the center of mass closer to the pivot to reduce the swing time slightly, overlooking the fact that the thread on the adjustment ring moved a smaller bar running through its center (which moved in the opposite direction when I screwed the ring towards the pivot). Physics+mechanical knowledge got it right on the next iteration.

I have had the clock running 1-second per hour too slow, and 1-second per hour too fast. Current thinking is that the pendulum is being slowed slightly when the cylinder passes on its slow fall (by increased air resistance). Yes dear reader, I have not been resetting the initial conditions before making a calibration run 😐

What else remains to learn, before summer heat has to be adjusted for?

While the clock face and hands may be great for attracting buyers, it has serious usability issues when it comes to telling the time. It is difficult to tell the time without paying more attention than normal; without being a few feet of the clock it is not possible to tell the time by just glancing at it. The see though nature of the face, the black-on-black of the end of the hour/minute hands, and the extension of the minute hand in the opposite direction all combine to really confuse the viewer.

A wire cutter solved the minute hand extension issue, and yellow fluorescent paint solved the black-on-black issue. Ravensburg clock with improved user interface, framed by faded paint of its predecessor below:

Ravensburg clock with improved user interface.

There is a discrete ting at the end of every hour. This could be slightly louder, and I plan to add some weight to the bell hammer. Had the bell been attached slightly off center, fine volume adjustment would have been possible.

Time-to-fix when mistake discovered in a later project phase

Derek Jones from The Shape of Code

Traditionally the management of software development projects divides them into phases, e.g., requirements, design, coding and testing. A mistake introduced in one phase may not be detected until a later phase. There is long-standing folklore that earlier mistakes detected in later phases are much much more costly to fix persists, despite the original source of this folklore being resoundingly debunked. Fixing a mistake later is likely to a bit more costly, but how much more costly? A lack of data prevents reliable analysis; this question also suffers from different projects having different cost-to-fix profiles.

This post addresses the time-to-fix question (cost involves all the resources needed to perform the fix). Does it take longer to correct mistakes when they are detected in phases that come after the one in which they were made?

The data comes from the paper: Composing Effective Software Security Assurance Workflows. The 35,367 (yes, thirty-five thousand) logged fixes, from 39 projects drawn from three organizations, contains information on: phases in which the mistake was made and fixed, time taken, person ID, project ID, date/time, plus other stuff :-)

Every project has its own characteristics that affect time-to-fix. Project 615, avionics software developed by organization A, has the most fixes (7,503) and is analysed here.

Avionics software is safety critical, and each major phase included its own review and inspection. The major phases include: requirements gathering, requirements analysis, high level design, design, coding, and testing. When counting the number of phases between introduction/fix, should review and inspection each count as a phase?

The primary reason for doing a review and inspection is to check the correctness (i.e., lack of mistakes) in the corresponding phase. If there is a time-to-fix penalty for mistakes found in these symbiotic-phases, I suspect it will be different from the time-to-fix penalty between major phases (which for simplicity, I’m assuming is major-phase independent).

The time-to-fix has a resolution of 1-minute, and some fix times are listed as taking a minute; 72% of fixes are recorded as taking less than 10-minutes. What kind of mistakes require less than 10-minutes to fix? Typos and other minutiae.

The plot below shows time-to-fix for mistakes having a given ‘distance’ between introduction/fix phase, for fixes taking at least 1, 5 and 10-minutes (code+data):

Time-to-fix for mistakes having a given number of phases between introduction and fix.

There is a huge variation in time-to-fix, and the regression lines (which have the form: fixTime approx e^{sqrt{phaseSep}}) explains just 6% of the variance in the data, i.e., there is a small increase with phase separation, but it is almost down in the noise.

All but one of the 38 people who worked on the project made multiple fixes (30 made more than 20 fixes), and may have got faster with practice. Adding the number of previous fixes by people making more than 20 fixes to the model gives: fixTime approx e^{sqrt{phaseSep}}/fixNum^{0.03}, and improves the model by less than 1-percent.

Fixing mistakes is a human activity, and individual performance often has a big impact on fitted models. Adding person ID to the model as a multiplication factor: i.e., fixTime approx personID*{e^{sqrt{phaseSep}}/fixNum^{0.03}}, improves the variance explained to 14% (better than a poke in the eye, just). The fitted value of personID varies between 0.66 and 1.4 (factor of two, human variation).

The answer to the time-to-fix question posed earlier (for project 615), is that it does take slightly longer to fix a mistake detected in phases occurring after the one in which the mistake was introduced. The phase difference is tiny, with differences in human performance having a bigger impact.

A 1948 viewpoint on developer vs. computer time

Derek Jones from The Shape of Code

For a long time now developer time has been a lot more expensive than computer time. The idea that developers should organize what they do, so as to maximize the efficiency of computer time rather than their own time, is considered to be an echo from a bygone age.

Until recently, I thought the transition from this bygone age, when computer time was considered more important than developer time, started in the late 1960s. Don’t ask me why I thought this, put it down to personal bias.

I was recently reading A Survey of Eniac Operations and Problems: 1946-1952, published in 1952, and what did I find:

“Early in 1948, R. F. Clippinger and some of his associates, in the course of coding the solution of …, were forced to adopt a different method of using the Eniac in order to fit their problem on the machine. …. The experience with this method (first discussed in reference 1), led J. von Neumann to suggest the use of a serial code for control of the Eniac. Such a code was devised and employed with the Eniac beginning in March 1948. Operation of the Eniac with this code was several times slower than either the original method of direct programming or the code for parallel operation. However, the resulting simplification of coding techniques and other advantages far outweighed this disadvantage.

In other words, in 1948, the people using one of the few computers in the world, which clocked at 100KHz, considered developer time to be more important than computer time.